Road piping project complete
Natalie McQuilken news-herald.net After four months of various delays, the Highland Avenue piping replacement project has been completed.
At a
Loudon Utilities Board meeting Oct. 28, community infrastructure
consultants W.K. Dickson & Co. Inc., informed the board that
Highland Avenue’s utility repair project was facing a setback
due to gas line placement.
The delay stemmed from gas lines that were not “tied on” at Webster Court. The project, which cost $1.1 million, had a goal to replace water and gas infrastructure and pave patchwork over utility lines beneath the road. Ryan Blake, W.K. Dickson vice president, said at the Oct. 28 meeting the company planned to make a new tap to extend from Webster Court to Highland Avenue. Though the discovery of "untied" lines put a bump in the plans, Blake believed finding the issue could have prevented future issues with the lines.
“Its purpose was to align
resources with (Tennessee Department of Transportation’s)
resurfacing program,” Ty Ross, LUB manager, said. “Highland
Avenue is a major connector street in Loudon, which makes it
eligible for state funding, and it was chosen as part of the
local programs offered by TDOT for paving.”
The board found replacing
water, sewer and gas lines would prepare for the repaving of
Highland Avenue, while also addressing the lines’ age before
breaks could occur.
“It’s a great alignment of
resources because ahead of that project, we were able to
replace the water, sewer and gas lines that were underneath
the road,” Ross said. “… It was just an opportune time to do
it ahead of the transportation resurfacing project.”
The project was finished Nov.
15, which was the date projected by Blake at the Oct. 28
meeting.
“The Highland Avenue
Water and Gas Replacement project was substantially
completed on Nov. 15,” Blake said in an email
correspondence. “The contractor is in the process of
removing any remaining equipment still stored on site
and addressing miscellaneous site cleanup items as
needed.”
The initial steps of the
next phase of the project, which includes resurfacing
Highland Avenue, can get underway. However, certain
processes need to take place before Highland Avenue sees
any paving.
“That will occur this
federal fiscal year,” Ross said. “The repaving will be
bid out soon and will likely occur in the spring when
the asphalt plants reopen.”
Unlike the piping
project, which spanned four months with various delays,
Ross expects the repaving process to have a shorter
timeline.
“It’s a very short time
compared to the pipeline replacement,” he said. “It’s
just basically paving over the top of what’s already
there alongside some sidewalk improvements, so that will
be not much. They’ll come in and we’ll bid it out (to) a
paving company, and they’ll be in and out in a matter of
days, if not weeks. Certainly, it won’t be a project at
the scope or scale of what was recently accomplished in
the past four months.”
|
BACK
12/18/19