North expansion needs reserve funds, BOE says
The cooling door, at a cost of $2,439, has been paid
out of a $10,000 contingency built into the project, which leaves
$7,561. However, the additional needs total $11,296.
An extra $2,253 was added to match the roofing
material to what is currently in place at NMS, bringing total added
costs to $13,549.
“There’s a transition between the new building and
the band room, and right now we’ve got shingles slated to be on
there,” Mike Garren, assistant director of schools, said. “So to
upgrade those shingles to a metal roof would be $2,200 and that
would match the metal coping. ... It would be less maintenance and
look a lot better. For the price it’s not a bad want.”
Rather than use the remainder of the contingency and
cut $6,000 in costs from other places, Vance suggested taking the
full $13,549 out of the school’s reserve funds, bringing the total
cost from the reserves to $160,549.
“If you didn’t use every penny of it, whatever
you didn’t use would go back in the fund balance after you were
finished with the duration of the project,” Vance said.
Taking that approach leaves the remainder of the
contingency for other unexpected expenses.
“If we eat all of our contingency up then we run
the risk of delaying the project one more time because we’ll
have to come back to the board one more time and get the county
commission’s permission to utilize our funds the way we think
need,” Vance said.
Craig Simon, BOE
chairman, questioned whether the county could be approached
to provide the $13,549 out of the Adequate Facilities Tax.
“I’m not saying you
can’t, that’s always a choice,” Vance said. “I just wouldn’t
because remember we asked for ($750,000) initially and they
said, ‘We’ll give you ($500,000) and you have to get the
rest on your own if you want it.’ So I would recommend that
we go $13,500 out of fund balance with the understanding
that if we don’t need it, it will just roll back into our
fund balance.”
Simon also suggested
waiting until the project is wrapping up to see if there is
need for additional funds. Gary Ubben, BOE vice chairman,
said the contractor would want the BOE to have the money on
hand before agreeing to additional work.
The BOE will vote on whether to approve the
funds Thursday during its regular meeting.
|
BACK
10/15/18