Renovations to the former SunTrust
building, which is slated to become
the new Lenoir City Hall, are nearly
complete as city officials prepare
for a moving date next month.
City Administrator Amber Scott said work inside the building is mostly finished.
Officials will still need to
conduct a walk-through with
contractor Wright Contracting
Inc., before moving can take
place, she said, noting that
company and city personnel will
likely meet next week. Moving
could take place as early as
Sept. 9.
“We’re going to do a weekend
move because we want to be the
least amount disruptive to the
public as possible, so we’re
getting close to that time,”
Scott said. “Right now,
everything is pretty much
completed. We have to do a final
walk-through with the contractor
to ensure our satisfaction of
the project. Just looking
forward to it.”
Lenoir City Council approved
pressure washing and a new coat
of paint placed on the exterior
of the building at the Aug. 8
city council meeting. Work is
being done by Knoxville-based
Riverbend Power Cleaning for
$14,800.
Scott said the pressure washing
has since been completed and a
focus has now been placed on
painting.
“They’re currently painting, and
that’s quite a process because
we’ve had to rent a high lift,”
Scott said. “There’s a lot of
area to cover there, and high up
as well, but I was surprised
just how well the building
looked just after being power
washed. I think I was by there
last week, and it made a
complete difference in my
opinion.”
The new city hall will have
additional parking spots on the
side and front of the building.
During last week’s city council
meeting, Parks and Recreation
Department Director Steve
Harrelson said Greenback Asphalt
Company was the lowest bidder on
four quotes submitted at
$20,985.
“I think it’s going to be great
for the public to see that and
for them to have a nice place to
come, something for the
community to be proud of,” Scott
said. “As you know, we’ve
currently outgrown our space
here. City hall’s been in this
building since 1988. Before that
time we were housed in the old
Lenoir City Utilities Board
building down here. They were
really squeezed into the LCUB
building and then moved here in
‘88. There’s going to be better
security at the new place.
There’s going to be a larger
courtroom, council chambers than
what we have now.”
Additional space will allow for
all departments to be under one
roof, and a new courtroom will
add about 30 percent more space
than the current location off
Broadway Street, Scott said.
“I guess the best thing that I
think is going to be an
improvement to what we’ve been
doing is that we’re going to be
able to start having a better
court system and going to have
at least three days of court
where we’ve only had one in the
past,” Councilman Eddie Simpson
said. “We do have now the room
and the facilities to be able to
bring the prisoners in and be
able to keep them occupied and
isolated and be able to go on
with the courts without
everybody sitting in there all
of them together, all the
prisoners in one area, the
holding cells inside the
courtroom.
“And we want to try to at some
point to start trying all the
drunk driving cases, maybe even
some civil issues and stuff like
that and help take some of the
load off (the) county court
system, and we’ll handle some of
our own,” he added.
Simpson said that overall, the
final tab for the city hall
project could cost about $1.7
million, which is significantly
lower than what city council
considered for a new building at
$6-$7 million.
“We’ve contemplated several
times to construct a new
building and when we found that
this SunTrust building was going
to become available we thought
it was a win-win situation to do
that and renovate it,” Simpson
said. “We were successful in
being able to do that and buy it
for a rather good price, which
was $700,000, and over the last
two years we’ve been able to
negotiate and get SunTrust out
and get them in a new building,
put them back on the tax roll,
and a really nice facility they
built.”
Hopes are to place an aquarium
inside for residents sometime in
the future, Simpson said.
“That’s my goal to try to push
for that,” Simpson said. “I just
think it’d be something really
good to look at. I’m not talking
huge, I’m just talking about
maybe a 2 foot by 4 foot or 2
foot by 6 foot, something
sitting on top of one of the
counters.”
Officials say nothing has been
decided on what will be done
with the current location.
“I’d like to see someone
interested in it take it because
it’s got a vault in it. It’s got
a downstairs,” Vice Mayor Jim
Shields said. “It could be used
for something, and the city may
want to use it and hang on to it
and use it for something else.
They’ve looked into that also. I
don’t know if maybe they decide
— everybody decides just to hang
on to it and use it for city
purposes for some other
department or something in the
future.
“Right now we’re just trying to
get this other one up and going
and working and hopefully we can
decide what we want to do with
the older building, either keep
it for a different department or
something or release it or sell
it,” he added.