U.S. 321 bridge project delayed again
After opening two lanes of the canal bridge on U.S.
Highway 321 in July, officials hoped to have all four lanes open by
year-end.
But that won’t happen, according to Mark Nagi,
Tennessee Department of Transportation communications officer.
“The earliest that four lanes would be open is in the
spring of 2018,” Nagi said in an email correspondence.
Delays in the project are nothing new. The project
was approved in 2012 at an estimated cost of $69.3 million and an
estimated completion date of May 31, 2015. Several other projected
finish dates have come and gone since.
Chad Woodruff, project manager for Blalock & Sons,
said in July that a sidewalk and parapet still needed to be
installed on the closed portion of the bridge before those lanes
could open. Tie-ins for new traffic flows are also still in
progress.
A shared pathway to allow pedestrian traffic to pass
across the bridge has slowed the project, Woodruff said Tuesday
morning. The pathway was not part of the original plan.
Because of that, traffic has not been able to shift
to the closed side of the bridge to allow for work on the ramps from
and to Tellico Village Parkway.
Hopes are to open one lane on each side of the bridge
soon to allow for work to be done on those ramps, but because colder
weather has started to move in, it is unlikely paving can be done
before April.
State Rep. Jimmy Matlock, R-Lenoir City, said the
further delay was “disappointing,” and hoped it would be the last.
“Finally, eventually we’re going to be able to get
this thing,” he said.
Demolition of the J. Carmichael Greer bridge over
Fort Loudoun Dam is in progress with an estimated completion date of
Feb. 28.
Mark Harrell, Loudon Parks and Recreation director,
informed Loudon City Council during a Nov. 13 workshop that a
portion of the bridge would be given to the city in order to build a
bridge in Loudon Municipal Park.
“We met with (Blalock & Sons) about the possibility
of getting some of the TVA dam bridge, the Fort Loudoun Dam bridge,”
Harrell said. “Discussion has been going on for a couple of years
with Jimmy Matlock’s office and it has come to fruition pretty fast.
... Basically they’re going to give us just about any of the steel
that we need to build the bridge across the creek.”
Matlock gave a majority of the credit for the
accomplishment to Harrell.
“I think the idea credit goes to Mark,” Matlock said.
“I was kind of the one that put all the parties together. Mark
thought since it was a part of the community for many years that it
could continue to be of use in some capacity.”
It is unclear whether the bridge in the municipal
park will be used for pedestrian or vehicle traffic since a review
from the Tennessee Department of Environment and Conservation is
still pending.
“It would have never happened if it weren’t for
the construction company, the Blalock family,” Matlock said.
“They came away in a big way with it.”
Construction starting soon
Work on the intersection of Highways 321 and 11
near downtown Lenoir City will begin before the end of the year,
with Nagi estimating a start date “the first week in December.”
J&M Grading Division LLC, the contractor for the
intersection project, has a pre-construction meeting scheduled
for Nov. 28, with signs going up that week to warn drivers of
construction.
“They’re widening 321 from approximately Simpson
Road down to the intersection,” Angie Davis, project manager for
J&M, said.
“Then they’ll have controlled access in the middle of that part. So there will be islands and curves. You’ll just have certain places you can turn and things like that.
“At the intersection they’re widening, putting
some drainage in,” she added. “It will have four signs like
what’s at the entrances to (the University of Tennessee) and
things like that, the big signs. There’s going to be some trash
cans and receptacles and things like that. So then you’ll have
some utilities that have to be moved as part of that.”
Completion for that portion of the project is set
for June 2018 when the contract with J&M concludes.
Nagi anticipates changes to traffic patterns will
coincide with work beginning in December and throughout the
remainder of the project.
“There will be a lot of work going on and we will
do our best to make everyone aware of anticipated traffic
pattern changes as they arise,” Nagi said.
|
BACK
7/27/17