Budget doubles for Queener
Road Parker Wright news-herald.net The Queener Road project is finally seeing some movement after being put off for years. The original plan for the project dates back to 2014 and was supposed to be completed in a three- to five-year window, Ty Ross, Loudon city manager, said. Ross said funding is part of the reason to blame on the delay.
“(Of the
project) 40 percent of Queener Road is federal dollars, 50 percent
is state dollars, only 10 percent local,” Ross said. “So we were
never driving the bus. It was always those larger funding sources.
Some of it has to do with annual budgets, and some of it’s just
political.”
The original project was
budgeted at $1.3 million. As of July 22, it is now estimated to
be $3.3 million due to engineers finding new areas for
improvements like a sidewalk spanning the full length of the
road.
“The city of Loudon wants
this road, so we were happy to triple our 10 percent, but going
to these other funding sources, that was difficult, but they’re
all on board now,” Ross said. “That’s the amended budget, so
we’re good to go.”
Officials are now waiting on a notice to proceed from the
Tennessee Department of Transportation. Ross said the city is
working to hire construction engineering and inspection services
from a list of TDOT approved inspectors. Construction cannot
proceed without this step, but utility relocation has begun.
Ross expects between
October and December a bid will be awarded for paving and
construction.
Loudon Mayor Jeff Harris
said not doing the project was never an option, even if federal
and state monies couldn’t be obtained. Jack Qualls, Loudon
County Economic Development Agency executive director, had the
right contacts and was able to facilitate conversation to get
everyone on board with the funding, he said.
“We would have to make
some adjustments and probably what we would have to do is I mean
we would take it out of the $4 million that we’re planning for
the paving project,” Harris said. “So some roads may not have
gotten the attention, may not have gotten paved, if we would’ve
had to take more money out of that for Queener Road. We’re
committed to finishing this Queener Road project.”
The project’s priority is
high among Loudon City Council, city employees and residents
along Queener Road.
“Whatever we say, it could
be a legitimate reason, but it just looks like an excuse,”
Harris said. “It’s going on so long now anything short of
getting it done, I don’t know that anybody’s going to have much
tolerance for, because it’s been so long, so many years. I mean
we, myself and the council that’s there now, inherited the
problem but we’ve got to finish it. We’re committed to it and
whatever it takes is what we’re going to do to get this thing
finished.”
|
BACK
9/7/20