Ahead of schedule, the new Dixie Lee Junction intersection opened for traffic Monday morning, Nov. 20.

However, “There is a lot of work left. … They still have to re-grade and pave Hwy 11 and 70,” stated Mark Nagi, TDOT Community Relations Officer, Region 1 (East Tennessee). “Also, they discovered an old concrete roadway under the existing roadway that will take some time to remove.

The job let at $3,496,631 [to Whaley & Sons, Inc., Kodak] and is currently at $3,609,270.96 due to some plans revisions.” Estimated completion date is “on or before Nov. 30, 2018,” Nagi further stated.