I have been contacted
by several people requesting an update on the road work on Highway 321
in Lenoir City. I am sure they're are many people interested in this
project. I requested an update from TDOT, and attached is their
response.
If I can be any
additional assistance, please let me know.
Sincerely,
Lowell
Russell
TN State Representative
District 21
Representative Russell:
From the Region:
Thank you for your comments regarding the State Route 73
(US-321) project in Lenoir City.
TDOT strives to assign enough working days to our project
to allow contractors ample time for completion but also desires
for projects to be constructed as efficiently and quickly as is
practically possible.
The referenced project was originally scheduled to be
completed June 30, 2019. There have been delays on this project caused
by a sinkhole, unforeseen utility conflicts, and a design
revision. These events are outside the control of the contractor, which
means that this contract is eligible for additional time to be added to
the contract completion date. Additional time can only be given in well
documented warranted cases, which are reviewed carefully by TDOT staff.
Because of these delays, the contract completion date has
been extended to August 4, 2019. We will continue to monitor this
schedule closely, and do everything we can to ensure that it is met.
Thanks,
Doug Gunnels |
TDOT Executive
Administrative Assistant |