Loudon County Board of Education is on target with two
construction projects, and board members hope a contract
dispute with Knoxville-based architect firm Weeks,
Ambrose & McDonald can be put aside so an addition can
be completed at Highland Park Elementary School.
The firm Cope Associates, Inc. Architecture showed
drawings of the proposed Loudon High School to BOE
members last Thursday during a workshop. The plan is to
build 12 classrooms, a new band room, two additional
science labs, a culinary arts room, additional dining
room space and a secure entryway in the front of the
building leading to the new office.
Loudon County Director of Schools Jason Vance said
an outside “park-type” setting will be featured
between the new addition and old building.
“It’ll give us an opportunity to bring all of our
teachers into one building, and it will give us
opportunities to do obviously some (science,
technology, engineering and mathematics) activities
that we’ve not been able to do in years past because
of our science labs not being up to date,” Vance
said. “So that’s going to be really, really
positive.”
Cope Associates representative Cayce Smith said the
main addition will be 33,340 square feet, and the
dining room area will be 3,368 square feet. She
anticipated the project would be put out to bid by
the end of the month, which is estimated to cost
$6.15 million.
“We’re putting the final touches on them now,” Vance
said. “I think that within the week they’ll have
them prepared to be approved by the fire marshal’s
office, and so after that we’ll be sending out the
bids, so I think we’re almost there.”
Vance estimated the fire marshal would review the
plans for about a week. If approved, the project
will then put out to bid and should take about three
weeks to award a contractor. He said he anticipated
dirt would be moved in November, and barring delays
the project would take about 1 1/2 years to
complete.
“We did a thorough needs assessment with community
representatives,” Ric Best, BOE chairman, said. “We
talked extensively with teachers, administrators. We
really believe that that plan is going to provide
the need for Loudon County students for at least the
next 25 years.”
Best said Cope Associates hadn’t told the estimated
capacity, but he believed it would be at least 900
students.
“The community has really supported the addition to
the high school,” Smith said in an email
correspondence. “Student safety is a top priority of
the school board and they have worked
collaboratively to provide solutions to the issues
their students face. We are proud to play a small
role to help the school board meet their goals of
academic achievement.”
Tech center coming along
Replacing the LCTC roof should take about four to
six months once a contractor has been awarded the
bid, Vance said.
“The LCTC roof project is currently out to bid,”
Smith said in an email correspondence. “We will
receive bids on Tuesday. The project schedule will
be determined by the selected general contractor and
the schedule they provide will be used in the
evaluation of the best bidder.”
Vance said he was hopeful the project would also
include replacement of the heating, ventilation and
air conditioning units on top of the building. The
project is estimated to cost less than $750,000 and
about $93,000 for HVAC unit replacement, he said,
adding the money would be taken out of the Adequate
Facilities Tax Fund.
“This board has been very conditioned about trying
to move as quickly as we can on projects and still
being prudent about making sure that we have a good
grasp on all the details of construction,” Best
said. “And whenever a project like that roof when
you’re dealing with an older building that has to be
examined and then modified, you’re putting new air
condition units in there, we would like for that to
move as fast as possible but we can’t make it move
any faster than it can.”
A new roof is needed, especially with a welding
vocational course being implemented in January,
Vance said.
Dispute ongoing
Vance said the only thing holding up work on
Highland Park Elementary School is a dispute with
Weeks, Ambrose & McDonald. The architecture firm
wants about $50,000, but school board members are
hesitant to pay the firm for something they don’t
believe is earned.
“Obviously we want to move on, but we also want to
make sure that basically we’re not paying Weeks,
Ambrose & McDonald for work that wasn’t even done,”
Jeremy Buckles, board member, said. “So I guess here
basically what has happened so far is the board has
voted not to pay them that extra around $50,000
because it was for work that they actually never
completed.”
Both parties were initially represented by attorney
Chuck Cagle but have sought legal counsel elsewhere.
Vance said Knoxville-based attorney Greg Logue was
retained by the school board a couple weeks ago
after it was determined the issue could not be
resolved.
During a workshop last week, Vance told board
members he hoped some middle ground could be found
so that the two parties could move forward with
selecting an architect firm and begin work.
“We have no question that we have a strong standing
to win an arbitration on the matter, but arbitration
is expensive for everyone and those are funds that
could be used ultimately for a school-based project
such as construction,” Best said. “So it’s just one
of those things where sometimes you just do what you
have to do.
“I don’t think that our board will agree to pay the
full amount that they’re asking for because it’s for
work they never did, and we’ve offered them what we
think is a fair and negotiated with a settlement to
be negotiated by an attorney and it’ll be up to the
other side,” he added. “The ball is more or less in
their court now.”
Best said the school board attorney has stated he
believes they are in “good standing,” however it
could cost more to prove they are right than it
would be to actually just pay an amount and move
forward.
“It’s really hard to see right now exactly where it
will wind up,” Buckles said. “We obviously want to
avoid going to court for getting in some situation
where it’s going to cost us more money than we would
wind up paying in the first place, so I think —
that’s me speaking right there, my thoughts on that
— but right now it’s kind of in the hands of our
attorneys.”
The school board has about $9.8 million to work with
on the LHS and HPES projects. Vance said he hopes
the issue with Weeks, Ambrose & McDonald can be
resolved by November so an architect can be awarded
the bid, begin drawing plans and send them to the
fire marshal’s office for approval.
“It’ll take a long time to do all the front end work
and then hopefully we’ll be able to start with
Highland Park sometime beginning of the next year,”
Vance said. “I’d like to be able to see us moving
forward with that one in the spring, sometime in the
spring of this upcoming year.”